Last Updated On: 15/12/2016  | 
Print Version

 

Project
Formation 
Surfacing
Resurfacing
Pmt Works
Maj Br 
Weighted %
Achieved
Achieved
Achieved
Achieved
Achieved
DEEPAK
60
86
99
77
36
66.86
SAMPARK
27
63
60
39
118
63.91
SHIVALIK
36
63
75
67
58
56.88
CHETAK
65
101
20
39
15
52.94
HIMANK
85
32
92
60
17
51.52
VIJAYAK
49
56
13
38
36
42.32
DANTAK
52
17
43
50
37
37.99
BEACON
22
36
54
46
39
36.37
SWASTIK
24
38
11
81
10
31.24
UDAYAK
14
43
27
24
21
25.79
VARTAK
31
32
20
23
10
23.60
BRAHMANK
9
22
9
25
26
18.85
SEWAK
35
10
5
19
12
17.48
PUSHPAK
37
6
6
23
5
15.97
STF HIRAK 
16
10
0
22
22
15.28
ARUNANK
21
19
6
9
9
14.20
SETUK
22
12
0
10
0
10.08
Note:-
Weighted percentage achievement has been calculated considering the weighted of works as under








Fmn-25%, Surf-25%, Pmt Works-15%, Maj Brs-25% and Resurf-10%







Weighted Percentage Progress =
0.25 x Fmn % prog + 0.25 Surf % prog + 0.15 x Pmt
 Wks % Prog +0.25 x maj Br % prog +0.10 x Resurf % Prog