Last Updated On: 15/12/2016  | 
Print Version

 

S/No. Project Allotment Expenditure utp Nov 2016
During the Month Total % Expdr 
1 ADG East 3.00 0.54 1.22 40.63
2 Beacon 356.32 29.98 270.47 75.91
3 Himank 371.67 40.39 269.94 72.63
4 Vijayak 165.19 30.91 120.25 72.80
5 Sampark 409.09 25.15 276.99 67.71
6 Deepak 190.12 12.57 146.60 77.11
7 Shivalik 309.54 25.18 197.95 63.95
8 Rohtang Tnl 410.58 18.00 122.00 29.71
9 Chetak 233.75 19.28 150.32 64.31
10 STF Hirak 104.24 10.86 50.43 48.38
11 Dantak 183.20 10.30 118.38 64.62
12 Vartak 287.92 49.30 234.52 81.45
13 Sewak 169.28 17.67 83.53 49.34
14 Pushpak 145.49 8.36 70.93 48.76
15 Udayak 223.30 21.11 159.92 71.62
16 Setuk 100.54 11.34 37.61 37.41
17 Swastik 244.00 22.62 177.06 72.56
18 Arunank 145.60 20.59 88.82 61.00
19 Brahmank 220.97 6.99 113.56 51.39
20 R&D Estt 3.00 0.06 1.82 60.61
  Total 4276.78 381.19 2692.30 62.95